Sprint 1: Foundation Modules & Modernization Implementation

Sprint Overview

Duration: 2 weeks
Goal: Achieve 100% test coverage for core utility modules while implementing key modernization objectives
Focus Areas: Utility Modules, Configuration, Service Registry, Neo4j Integration

Strategic Approach

This sprint implements our module-focused testing strategy while advancing modernization goals:

  1. Incremental Progress: Complete 100% test coverage for one module before moving to the next
  2. Build Momentum: Begin with smaller, simpler modules first
  3. Quality First: Ensure all code follows SOLID principles and includes comprehensive type annotations
  4. Modernization Implementation: Apply consistent modernization patterns from our plan

Modernization Goals for Sprint 1

  1. Type Annotation Modernization
    • Convert all annotations to modern syntax (dict, list, X | None)
    • Add Protocol interfaces for service contracts
    • Use Final for constants
    • Add TypedDict for complex dictionaries
  2. Dependency Injection & Service Registry
    • Consolidate service registry implementations
    • Implement consistent dependency injection pattern
    • Use Protocol interfaces for dependency contracts
  3. Error Handling & Validation
    • Create standardized error hierarchies
    • Implement consistent error propagation patterns
    • Add Pydantic validation for configuration models
  4. Documentation & Code Quality
    • Standardize docstring format across all modules
    • Add module-level docstrings explaining purpose
    • Apply consistent naming conventions

Technical Tasks Breakdown

1. Environment Module Completion (2 days)

Current Status: 49% test coverage

Tasks:

Tests:

2. Utils Package Initialization (1 day)

Current Status: 75% test coverage

Tasks:

Tests:

3. Service Registry Consolidation (4 days)

Current Status: 58% test coverage

Tasks:

Tests:

4. Configuration Registry Consolidation (3 days)

Current Status: 52% test coverage

Tasks:

Tests:

5. Secret Manager Completion (2 days)

Current Status: 59% test coverage

Tasks:

Tests:

6. Neo4j Integration Preparation (3 days)

Current Status: Modernization in archive

Tasks:

Tests:

7. Application Main Entry Points (1 day)

Current Status: 0% test coverage

Tasks:

Tests:

Definition of Done

Progress Tracking

Module Starting Coverage Target Modernization Status Completed
environment.py 49% 100% Type annotations needed [ ]
utils/init.py 75% 100% Docstrings needed [ ]
service_registry.py 58% 100% Needs consolidation [ ]
config_registry.py 52% 100% Needs consolidation [ ]
secret_manager.py 59% 100% Error handling needed [ ]
Neo4j interfaces N/A 100% Protocol interfaces needed [ ]
main.py 0% 100% Not started [ ]

Next Sprint Preview

After completing this sprint, we will have a solid foundation of core utility modules with 100% test coverage and modern implementation patterns. The next sprint will focus on:

  1. Complete Neo4j integration with connection management
  2. Repository pattern implementation using Protocol interfaces
  3. Transaction management and error handling
  4. Continue modernization efforts for database operations